Blundell
Geothermal power plant in Beaver County, Utah. 38.1 MW of nameplate capacity across 2 generators, operated by PacifiCorp.
Also known as Blundell Plant · EIA plant 299
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 38.1 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- July 1984First generator online
- Operator
- PacifiCorpEIA operator ID 14354
- Grid
- PACEBalancing authority PACE
- Price nodes
- None linkedNo verified ISO node
- Location
- Beaver County, UT38.4889, −112.8533
- EIA plant ID
- 299EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Blundell produces
Free · EIA-923Net generation, 2025
271 GWh
271,209 MWh, final
Capacity factor, 2025
81.3%
2024: 81.4%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
115.2–272.5
GWh a year. Low 2019, high 2024
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | 151,843 | Not reported | 12 of 12 |
| 2001 | 152,742 | Not reported | 12 of 12 |
| 2002 | 184,447 | Not reported | 12 of 12 |
| 2003 | 198,465 | Not reported | 12 of 12 |
| 2004 | 194,876 | Not reported | 12 of 12 |
| 2005 | 184,802 | Not reported | 12 of 12 |
| 2006 | 190,608 | Not reported | 12 of 12 |
| 2007 | 163,925 | Not reported | 12 of 12 |
| 2008 | 254,277 | Not reported | 12 of 12 |
| 2009 | 279,121 | Not reported | 12 of 12 |
| 2010 | 274,358 | 82.2% | 12 of 12 |
| 2011 | 278,080 | 83.3% | 12 of 12 |
| 2012 | 268,542 | 80.2% | 12 of 12 |
| 2013 | 250,722 | 75.1% | 12 of 12 |
| 2014 | 274,996 | Not reported | 12 of 12 |
| 2015 | 259,703 | 66.2% | 12 of 12 |
| 2016 | 256,918 | 65.3% | 12 of 12 |
| 2017 | 249,033 | 63.5% | 12 of 12 |
| 2018 | 223,051 | 56.8% | 12 of 12 |
| 2019 | 115,179 | 29.3% | 12 of 12 |
| 2020 | 175,570 | 44.6% | 12 of 12 |
| 2021 | 211,226 | 53.8% | 12 of 12 |
| 2022 | 262,129 | 66.8% | 12 of 12 |
| 2023 | 248,201 | Not reported | 12 of 12 |
| 2024 | 272,457 | 81.4% | 12 of 12 |
| 2025 | 271,209 | 81.3% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Geothermal | 26.1 | July 1984 |
| 2 | Geothermal | 12.0 | December 2007 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists PacifiCorp as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Blundell and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Blundell
More plants operated by PacifiCorp
Questions about Blundell
How much power does Blundell produce?
Blundell reported 271,209 MWh (271 GWh) of net generation in 2025, a 81.3% capacity factor on 38.1 MW of nameplate capacity.
Where is Blundell?
Blundell is in Beaver County, Utah, at 38.4889, −112.8533. It is in the PacifiCorp - East balancing area (PACE).
Who operates Blundell?
EIA-860M for August 2026 lists PacifiCorp as the operator (EIA operator ID 14354). The operator is not always the owner.
When did Blundell start operating?
Its first generator began operating in July 1984, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page