Natural gasSolarOperatingSRP

Copper Crossing Energy and Research Cent

Natural gas and solar power plant in Pinal County, Arizona. 153.4 MW of nameplate capacity across 5 generators, operated by Salt River Project.

Also known as EIA plant 58413

Analyst: free account, 1 question a day.

Banner Solar IronwoodBox Canyon (AZ)Sandstone SolarQueen Creek Solar FarmBonnybrooke PVCopper Crossing Energ…10 km
Open in the map
6 plants within 17 km, from EIA coordinates.

Key facts

Capacity
153.4 MWNatural gas 99.0 · Solar 54.4
Generators
5 operatingEIA-860M, August 2026
Operating since
May 2024First generator online
Operator
Salt River ProjectEIA operator ID 16572
Grid
SRPBalancing authority SRP
Price nodes
None linkedNo verified ISO node
Location
Pinal County, AZ33.1551, −111.4836
EIA plant ID
58413EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Copper Crossing Energy and Research Cent produces

Free · EIA-923

Net generation, 2025

4.32 GWh

4,320 MWh, final

Capacity factor, 2025

Not reported

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
20245,083Not reported7 of 12
20254,320Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

2,712

US short tons. 2024: 5,075

SO₂, 2025

0

US short tons

NOx, 2025

1

US short tons

CO₂ per MWh, calculated

0.63 t

About 1,256 lb per MWh

2 of 2 EPA units reported CO₂ in 2025 (SCCT1, SCCT2), matched to EIA plant 58413 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CXGT1Natural Gas Fired Combustion Turbine49.5May 2024
CXGT2Natural Gas Fired Combustion Turbine49.5May 2024
CXS01Solar Photovoltaic17.6March 2026
CXS02Solar Photovoltaic17.6March 2026
CXS03Solar Photovoltaic19.2March 2026

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Salt River Project as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Copper Crossing Energy and Research Cent and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Copper Crossing Energy and Research Cent

More plants operated by Salt River Project

Questions about Copper Crossing Energy and Research Cent

How much power does Copper Crossing Energy and Research Cent produce?

Copper Crossing Energy and Research Cent reported 4,320 MWh (4.32 GWh) of net generation in 2025.

Where is Copper Crossing Energy and Research Cent?

Copper Crossing Energy and Research Cent is in Pinal County, Arizona, at 33.1551, −111.4836. It is in the Salt River Project balancing area (SRP).

Who operates Copper Crossing Energy and Research Cent?

EIA-860M for August 2026 lists Salt River Project as the operator (EIA operator ID 16572). The operator is not always the owner.

Is Copper Crossing Energy and Research Cent a natural gas or a solar plant?

Both. Natural gas capacity totals 99 MW and solar capacity totals 54.4 MW.

When did Copper Crossing Energy and Research Cent start operating?

Its first generator began operating in May 2024, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page