SolarBattery storageOperatingAZPS

Desert Star Hybrid

Solar and battery storage project in Maricopa County, Arizona. 20 MW of nameplate capacity across 2 generators, operated by Arizona Public Service Co.

Also known as EIA plant 59444

This project groups Desert Star Hybrid (EIA 59444). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Cotton Center Solar HybridRE Gillespie 1 LLCSonoran Solar EnergyGila River Power Block 4Desert Star Hybrid10 km
Open in the map
6 plants within 19 km, from EIA coordinates.

Key facts

Capacity
20 MWSolar 10.0 · Battery storage 10.0
Generators
2 operatingEIA-860M, August 2026
Operating since
September 2015First generator online
Operator
Arizona Public Service CoEIA operator ID 803
Grid
AZPSBalancing authority AZPS
Price nodes
None linkedNo verified ISO node
Location
Maricopa County, AZ33.1450, −112.6600
EIA plant ID
59444EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Desert Star Hybrid produces

Free · EIA-923

Net generation, 2025

24.2 GWh

24,237 MWh, final

Capacity factor, 2025

30.0%

2024: 35.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2016 to 2025

8.9–32.4

GWh a year. Low 2016, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
201514,81747.2%4 of 12
20168,92410.2%12 of 12
201717,27319.7%12 of 12
201829,69033.9%12 of 12
201931,00635.4%12 of 12
202032,43136.9%12 of 12
202131,62736.1%12 of 12
202230,91235.3%12 of 12
202328,399Not reported11 of 12
202429,16335.4%12 of 12
202524,23730.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
DS10MBatteries10.0February 2023
PV1Solar Photovoltaic10.0September 2015

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Arizona Public Service Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Desert Star Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Desert Star Hybrid

More plants operated by Arizona Public Service Co

Questions about Desert Star Hybrid

How much power does Desert Star Hybrid produce?

Desert Star Hybrid reported 24,237 MWh (24.2 GWh) of net generation in 2025, a 30.0% capacity factor on 20 MW of nameplate capacity.

Where is Desert Star Hybrid?

Desert Star Hybrid is in Maricopa County, Arizona, at 33.1450, −112.6600. It is in the Arizona Public Service Company balancing area (AZPS).

Who operates Desert Star Hybrid?

EIA-860M for August 2026 lists Arizona Public Service Co as the operator (EIA operator ID 803). The operator is not always the owner.

Is Desert Star Hybrid a solar or a battery storage plant?

Both. Solar capacity totals 10 MW and battery storage capacity totals 10 MW.

When did Desert Star Hybrid start operating?

Its first generator began operating in September 2015, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page