SolarOperatingISO-NE

GMP Solar - Williston

Solar power plant in Chittenden County, Vermont. 4.7 MW of nameplate capacity across 1 generator, operated by Green Mountain Power Corp.

Also known as GMP Solar-Williston · EIA plant 60875

Analyst: free account, 1 question a day.

Essex Junction 19Whitcomb Solar FarmChittenden County Solar PartnersGorge 18GMP Solar - Williston2 km
Open in the map
6 plants within 6.0 km, from EIA coordinates.

Key facts

Capacity
4.7 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
November 2016First generator online
Operator
Green Mountain Power CorpEIA operator ID 7601
Grid
ISO-NEBalancing authority ISNE
Price nodes
None linkedNo verified ISO node
Location
Chittenden County, VT44.4655, −73.1032
EIA plant ID
60875EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power GMP Solar - Williston produces

Free · EIA-923

Net generation, 2025

6.19 GWh

6,185 MWh, final

Capacity factor, 2025

15.0%

2024: 16.7%

January to July 2026

3.81 GWh

Provisional

Range, 2017 to 2025

6.2–7.2

GWh a year. Low 2025, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016136Not reported2 of 12
20176,79616.5%12 of 12
20186,90316.8%12 of 12
20197,20117.5%12 of 12
20207,19819.0%11 of 12
20216,83016.6%12 of 12
20227,17417.4%12 of 12
20236,76716.4%12 of 12
20246,89116.7%12 of 12
20256,18515.0%12 of 12
2026 (provisional, partial year)3,80915.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GMPSWSolar Photovoltaic4.7November 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Green Mountain Power Corp as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query GMP Solar - Williston and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near GMP Solar - Williston

More plants operated by Green Mountain Power Corp

Questions about GMP Solar - Williston

How much power does GMP Solar - Williston produce?

GMP Solar - Williston reported 6,185 MWh (6.19 GWh) of net generation in 2025, a 15.0% capacity factor on 4.7 MW of nameplate capacity. From January to July 2026 it reported 3.81 GWh, which is provisional.

Where is GMP Solar - Williston?

GMP Solar - Williston is in Chittenden County, Vermont, at 44.4655, −73.1032. It is in the ISO New England Inc. balancing area (ISNE).

Who operates GMP Solar - Williston?

EIA-860M for August 2026 lists Green Mountain Power Corp as the operator (EIA operator ID 7601). The operator is not always the owner.

When did GMP Solar - Williston start operating?

Its first generator began operating in November 2016, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page