Key facts

Capacity
2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 2018First generator online
Operator
Town of Braintree - (MA)EIA operator ID 2144
Grid
ISO-NEBalancing authority ISNE
Price nodes
None linkedNo verified ISO node
Location
Norfolk County, MA42.1877, −70.9764
EIA plant ID
62257EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Station 9 Energy Storage System produces

Free · EIA-923

Net generation, 2025

−29 MWh

−29 MWh, final

Battery discharge, 2025

326 MWh

Charge 354 MWh

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

−103.0–−29.0

MWh a year. Low 2021, high 2025

Annual net generation, MWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018−33Not reported7 of 12
2019−64Not reported12 of 12
2020−69Not reported12 of 12
2021−103Not reported12 of 12
2022−102Not reported12 of 12
2023−98Not reported12 of 12
2024−98Not reported12 of 12
2025−29Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ESS1Batteries2.0June 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Town of Braintree - (MA) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Station 9 Energy Storage System and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Station 9 Energy Storage System

More plants operated by Town of Braintree - (MA)

Questions about Station 9 Energy Storage System

How much power does Station 9 Energy Storage System produce?

Station 9 Energy Storage System reported −29 MWh (−29 MWh) of net generation in 2025.

Where is Station 9 Energy Storage System?

Station 9 Energy Storage System is in Norfolk County, Massachusetts, at 42.1877, −70.9765. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Station 9 Energy Storage System?

EIA-860M for August 2026 lists Town of Braintree - (MA) as the operator (EIA operator ID 2144). The operator is not always the owner.

When did Station 9 Energy Storage System start operating?

Its first generator began operating in June 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)