Battery storageOperatingNYISO

98th Street Battery Storage Station

Battery storage project in Queens County, New York. 2 MW of nameplate capacity across 1 generator, operated by Consolidated Edison Co-NY Inc.

Also known as EIA plant 62839

Analyst: free account, 1 question a day.

MER QueensKennedy International Airport Cogen55 Drive BESSNHH003 Clarkson Fuel Cell98th Street Battery S…5 km
Open in the map
6 plants within 9.2 km, from EIA coordinates.

Key facts

Capacity
2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 2021First generator online
Operator
Consolidated Edison Co-NY IncEIA operator ID 4226
Grid
NYISOBalancing authority NYIS
Price nodes
None linkedNo verified ISO node
Location
Queens County, NY40.6791, −73.8402
EIA plant ID
62839EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power 98th Street Battery Storage Station produces

Free · EIA-923

Net generation, 2025

−175 MWh

−175 MWh, final

Battery discharge, 2025

149 MWh

Charge 324 MWh

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2022 to 2025

−308.0–16.0

MWh a year. Low 2024, high 2022

Annual net generation, MWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
202180Not reported7 of 12
202216Not reported12 of 12
2023−158Not reported12 of 12
2024−308Not reported12 of 12
2025−175Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ESS98Batteries2.0June 2021

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Consolidated Edison Co-NY Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query 98th Street Battery Storage Station and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near 98th Street Battery Storage Station

More plants operated by Consolidated Edison Co-NY Inc

Questions about 98th Street Battery Storage Station

How much power does 98th Street Battery Storage Station produce?

98th Street Battery Storage Station reported −175 MWh (−175 MWh) of net generation in 2025.

Where is 98th Street Battery Storage Station?

98th Street Battery Storage Station is in Queens County, New York, at 40.6791, −73.8402. It is in the New York Independent System Operator balancing area (NYIS).

Who operates 98th Street Battery Storage Station?

EIA-860M for August 2026 lists Consolidated Edison Co-NY Inc as the operator (EIA operator ID 4226). The operator is not always the owner.

When did 98th Street Battery Storage Station start operating?

Its first generator began operating in June 2021, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page