Battery storageOperatingNYISO

Brownsville Energy Storage System

Battery storage project in Kings County, New York. 5.6 MW of nameplate capacity across 1 generator, operated by Consolidated Edison Co-NY Inc.

Also known as EIA plant 68346

Analyst: free account, 1 question a day.

NHH003 Clarkson Fuel Cell98th Street Battery Storage Station55 Drive BESSNewYork-Presbyterian…Brownsville Energy St…2 km
Open in the map
6 plants within 6.8 km, from EIA coordinates.

Key facts

Capacity
5.6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2025First generator online
Operator
Consolidated Edison Co-NY IncEIA operator ID 4226
Grid
NYISOBalancing authority NYIS
Price nodes
None linkedNo verified ISO node
Location
Kings County, NY40.6695, −73.8985
EIA plant ID
68346EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Brownsville Energy Storage System produces

Free · EIA-923

Net generation, 2025

0 MWh

0 MWh, final

Battery discharge, 2025

0 MWh

Charge 0 MWh

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Annual net generation, MWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024Not reportedNot reported0 of 12
20250Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ESSBRBatteries5.6September 2025

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Consolidated Edison Co-NY Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Brownsville Energy Storage System and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Brownsville Energy Storage System

More plants operated by Consolidated Edison Co-NY Inc

Questions about Brownsville Energy Storage System

How much power does Brownsville Energy Storage System produce?

Brownsville Energy Storage System reported 0 MWh (0 MWh) of net generation in 2025.

Where is Brownsville Energy Storage System?

Brownsville Energy Storage System is in Kings County, New York, at 40.6695, −73.8985. It is in the New York Independent System Operator balancing area (NYIS).

Who operates Brownsville Energy Storage System?

EIA-860M for August 2026 lists Consolidated Edison Co-NY Inc as the operator (EIA operator ID 4226). The operator is not always the owner.

When did Brownsville Energy Storage System start operating?

Its first generator began operating in September 2025, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page