Natural gasOperatingNYISO

East River

Natural gas power plant in New York County, New York. 716.2 MW of nameplate capacity across 4 generators, operated by Consolidated Edison Co-NY Inc.

Also known as Con Edison East River Generating Station · EIA plant 2493

Analyst: free account, 1 question a day.

North 1stNYU LANGONE HEALTHAE-ESS NWS 1, LLCPeak Power 1 CogenOBP CogenOak OrchardEast River2 km
Open in the map
6 plants within 3.2 km, from EIA coordinates.

Key facts

Capacity
716.2 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
November 1951First generator online
Operator
Consolidated Edison Co-NY IncEIA operator ID 4226
Grid
NYISOBalancing authority NYIS
Price nodes
4 NYISO nodesResource nodes with prices
Location
New York County, NY40.7281, −73.9742
EIA plant ID
2493EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power East River produces

Free · EIA-923

Net generation, 2025

2.75 TWh

2,753,658 MWh, final

Capacity factor, 2025

43.9%

2024: 46.0%

January to July 2026

1.51 TWh

Provisional. 6 of 7 months reported

Range, 2015 to 2025

2.8–3.1

TWh a year. Low 2025, high 2020

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000570,216Not reported12 of 12
2001732,011Not reported12 of 12
2002737,620Not reported12 of 12
2003573,429Not reported12 of 12
2004933,191Not reported12 of 12
20052,087,967Not reported12 of 12
20062,542,694Not reported11 of 12
20072,803,889Not reported12 of 12
20082,854,807Not reported12 of 12
20092,450,311Not reported12 of 12
20103,285,431Not reported12 of 12
20112,746,244Not reported12 of 12
20123,074,43848.9%12 of 12
20133,182,29550.7%12 of 12
20142,753,99143.9%12 of 12
20152,927,989Not reported12 of 12
20163,081,69449.0%12 of 12
20173,093,06049.3%12 of 12
20182,955,25847.1%12 of 12
2019294,15655.2%1 of 12
20203,120,89949.6%12 of 12
2021Not reportedNot reported0 of 12
20223,011,08148.0%12 of 12
20233,078,70749.1%12 of 12
20242,894,11946.0%12 of 12
20252,753,65843.9%12 of 12
2026 (provisional, partial year)1,505,31448.4%6 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · NYISO

Emissions

Free · EPA CAMPD

CO₂, 2025

2.01M

US short tons. 2024: 2.08M

SO₂, 2025

22

US short tons

NOx, 2025

713

US short tons

CO₂ per MWh, calculated

0.73 t

About 1,460 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (1, 2, 60, 70), matched to EIA plant 2493 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

65,179

million gallons

Consumption, 2024

0

million gallons

Source

East River

Surface, Fresh. Once-through

Watershed stress

Very low/none · 0.138

USGS SUI, HUC12 East River-Hudson River

24 of 24 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas Fired Combustion Turbine180.0April 2005
2Natural Gas Fired Combustion Turbine180.0April 2005
6Natural Gas Steam Turbine156.2November 1951
7Natural Gas Steam Turbine200.0June 1955

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Consolidated Edison Co-NY Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query East River and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near East River

More plants operated by Consolidated Edison Co-NY Inc

Questions about East River

How much power does East River produce?

East River reported 2,753,658 MWh (2.75 TWh) of net generation in 2025, a 43.9% capacity factor on 716.2 MW of nameplate capacity. From January to July 2026 it reported 1.51 TWh, which is provisional.

Where is East River?

East River is in New York County, New York, at 40.7281, −73.9742. It is in the New York Independent System Operator balancing area (NYIS).

Who operates East River?

EIA-860M for August 2026 lists Consolidated Edison Co-NY Inc as the operator (EIA operator ID 4226). The operator is not always the owner.

When did East River start operating?

Its first generator began operating in November 1951, according to EIA-860M.

Does InfraMap have power prices for East River?

Yes. InfraMap has NYISO day-ahead and real-time prices at 4 price nodes linked to East River, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • NYISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page