HydroOperatingCPLE

Tillery

Hydro power plant in Montgomery County, North Carolina. 84 MW of nameplate capacity across 4 generators, operated by Duke Energy Progress - (NC).

Also known as Tillery Dam · EIA plant 2714

Analyst: free account, 1 question a day.

Fisher Solar Farm - NCGileadWadesboro 4CopperfieldUwharrie Mountain Ren…Stanly Solar, LLCTillery10 km
Open in the map
6 plants within 18 km, from EIA coordinates.

Key facts

Capacity
84 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
August 1928First generator online
Operator
Duke Energy Progress - (NC)EIA operator ID 3046
Grid
CPLEBalancing authority CPLE
Price nodes
None linkedNo verified ISO node
Location
Montgomery County, NC35.2067, −80.0648
EIA plant ID
2714EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Tillery produces

Free · EIA-923

Net generation, 2025

118 GWh

117,676 MWh, final

Capacity factor, 2025

16.0%

2024: 25.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

117.7–316.8

GWh a year. Low 2025, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000109,198Not reported12 of 12
200176,933Not reported12 of 12
2002115,544Not reported12 of 12
2003317,505Not reported12 of 12
2004189,713Not reported12 of 12
2005185,546Not reported12 of 12
2006146,425Not reported12 of 12
2007125,588Not reported12 of 12
2008103,803Not reported12 of 12
2009191,597Not reported12 of 12
2010189,58025.8%12 of 12
2011145,16219.7%12 of 12
2012136,28618.5%12 of 12
2013248,64333.8%12 of 12
2014182,18224.8%12 of 12
2015158,13721.5%12 of 12
2016152,38420.7%12 of 12
2017117,83516.0%12 of 12
2018238,60832.4%12 of 12
2019232,72031.6%12 of 12
2020316,75642.9%12 of 12
2021188,15725.6%12 of 12
2022153,41420.8%12 of 12
2023166,39522.6%12 of 12
2024184,24825.0%12 of 12
2025117,67616.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric22.0August 1928
2Conventional Hydroelectric18.0August 1928
3Conventional Hydroelectric22.0August 1928
4Conventional Hydroelectric22.0June 1960

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Duke Energy Progress - (NC) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Tillery and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Tillery

More plants operated by Duke Energy Progress - (NC)

Questions about Tillery

How much power does Tillery produce?

Tillery reported 117,676 MWh (118 GWh) of net generation in 2025, a 16.0% capacity factor on 84 MW of nameplate capacity.

Where is Tillery?

Tillery is in Montgomery County, North Carolina, at 35.2067, −80.0648. It is in the Duke Energy Progress East balancing area (CPLE).

Who operates Tillery?

EIA-860M for August 2026 lists Duke Energy Progress - (NC) as the operator (EIA operator ID 3046). The operator is not always the owner.

When did Tillery start operating?

Its first generator began operating in August 1928, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page