NuclearOperatingCPLE

Brunswick Nuclear

Nuclear power plant in Brunswick County, North Carolina. 2,003.2 MW of nameplate capacity across 2 generators, operated by Duke Energy Progress - (NC).

Also known as Brunswick Nuclear Generating Station · EIA plant 6014

Analyst: free account, 1 question a day.

Zion Hill BESSAGA TAG Solar IV LLCL V Sutton Combined CycleBrunswick Nuclear20 km
Open in the map
6 plants within 37 km, from EIA coordinates.

Key facts

Capacity
2,003.2 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
November 1975First generator online
Operator
Duke Energy Progress - (NC)EIA operator ID 3046
Grid
CPLEBalancing authority CPLE
Price nodes
None linkedNo verified ISO node
Location
Brunswick County, NC33.9597, −78.0114
EIA plant ID
6014EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Brunswick Nuclear produces

Free · EIA-923

Net generation, 2025

15.7 TWh

15,710,695 MWh, final

Capacity factor, 2025

89.5%

2024: 88.8%

January to July 2026

8.40 TWh

Provisional

Range, 2015 to 2025

14.6–15.7

TWh a year. Low 2018, high 2025

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200013,801,532Not reported12 of 12
200113,843,547Not reported12 of 12
200213,777,445Not reported12 of 12
200314,729,520Not reported12 of 12
200414,849,660Not reported12 of 12
200514,536,748Not reported12 of 12
200614,542,089Not reported12 of 12
200715,022,163Not reported12 of 12
200814,884,870Not reported12 of 12
200914,429,807Not reported12 of 12
201014,808,48884.4%12 of 12
201114,565,06083.0%12 of 12
201214,303,07581.3%12 of 12
201314,455,76882.4%12 of 12
201415,332,24087.4%12 of 12
201515,288,58287.1%12 of 12
201615,388,74787.5%12 of 12
201715,370,15587.6%12 of 12
201814,626,96783.4%12 of 12
201914,716,75683.9%12 of 12
202015,006,22085.3%12 of 12
202115,468,86088.2%12 of 12
202215,387,10587.7%12 of 12
202315,658,07689.2%12 of 12
202415,625,55088.8%12 of 12
202515,710,69589.5%12 of 12
2026 (provisional, partial year)8,401,74382.4%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

505,994

million gallons

Consumption, 2024

0

million gallons

Source

Atlantic Ocean (Cape Fear)

Surface, Saline. Once-through

Watershed stress

Very low/none · 0.159

USGS SUI, HUC12 Walden Creek

24 of 24 cooling months report withdrawal. Saline, brackish or ocean intake; not tested. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Nuclear1,001.6March 1977
2Nuclear1,001.6November 1975

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Duke Energy Progress - (NC) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Brunswick Nuclear and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Brunswick Nuclear

More plants operated by Duke Energy Progress - (NC)

Questions about Brunswick Nuclear

How much power does Brunswick Nuclear produce?

Brunswick Nuclear reported 15,710,695 MWh (15.7 TWh) of net generation in 2025, a 89.5% capacity factor on 2,003.2 MW of nameplate capacity. From January to July 2026 it reported 8.40 TWh, which is provisional.

Where is Brunswick Nuclear?

Brunswick Nuclear is in Brunswick County, North Carolina, at 33.9597, −78.0114. It is in the Duke Energy Progress East balancing area (CPLE).

Who operates Brunswick Nuclear?

EIA-860M for August 2026 lists Duke Energy Progress - (NC) as the operator (EIA operator ID 3046). The operator is not always the owner.

When did Brunswick Nuclear start operating?

Its first generator began operating in November 1975, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page