Hydroelectric power plants in Massachusetts
28 operating hydroelectric power plants in Massachusetts with 265 MW of hydroelectric capacity, largest first. From EIA-860M, August 2026.
Plants
28
Hydroelectric capacity
265 MW
Net generation, 2025
756 GWh
26 of 28 plants reported
Largest hydroelectric power plants in Massachusetts
| # | Plant | Hydroelectric MW | GWh, 2025 | Capacity factor |
|---|---|---|---|---|
| 1 | CabotFranklin County | 62 | 239 | 44.2% |
| 2 | Hadley FallsHampden County | 33 | 137 | 46.9% |
| 3 | Cobble MountainHampden County | 33 | 7.1 | 2.4% |
| 4 | Boott HydropowerMiddlesex County | 23 | 60.8 | 30.3% |
| 5 | Deerfield 5Berkshire County | 18 | 44.4 | 29.0% |
| 6 | Lawrence Hydroelectric AssociatesEssex County | 15 | 58.9 | 45.4% |
| 7 | Fife BrookBerkshire County | 11 | 0.0 | – |
| 8 | ShermanFranklin County | 7.2 | 27.8 | 44.2% |
| 9 | Riverside HolyokeHampden County | 6.9 | 22.5 | 37.2% |
| 10 | Turners FallsFranklin County | 5.7 | 11.8 | 23.7% |
| 11 | Deerfield 2Franklin County | 4.8 | 29.4 | 70.0% |
| 12 | Deerfield 3Franklin County | 4.8 | 26.5 | 62.9% |
| 13 | Deerfield 4Franklin County | 4.8 | 21.5 | 51.1% |
| 14 | Indian OrchardHampden County | 3.7 | 3.5 | 10.7% |
| 15 | Gardners FallsFranklin County | 3.5 | 11.4 | 37.2% |
| 16 | Oakdale Power StationWorcester County | 3.5 | 1.4 | 4.4% |
| 17 | Putts BridgeHampden County | 3.2 | 10.6 | 37.7% |
| 18 | Cosgrove Intake and Power StationWorcester County | 3.2 | 0.0 | 0.1% |
| 19 | BoatlockHampden County | 3.1 | 11.6 | 42.7% |
| 20 | International Paper Woronoco MillHampden County | 2.8 | 6.6 | 27.0% |
| 21 | Cabot HolyokeHampden County | 2.6 | 3.0 | 13.0% |
| 22 | Pepperell Hydro Power PlantMiddlesex County | 2.2 | 3.8 | 19.5% |
| 23 | ChemicalHampden County | 1.6 | 5.1 | 36.7% |
| 24 | Texon Hydroelectric ProjectHampden County | 1.5 | 3.9 | 29.9% |
| 25 | Indian River HydroHampden County | 1.4 | 1.8 | 14.7% |
| 26 | DwightHampden County | 1.2 | 5.6 | 53.2% |
| 27 | Collins FacilityHampden County | 1.2 | – | – |
| 28 | Glendale Hydroelectric ProjectBerkshire County | 1.1 | – | – |
Projects where hydroelectric is the largest fuel or at least a fifth of nameplate capacity. MW is hydroelectric nameplate only; net generation covers the whole project. Source: EIA-860M August 2026, published 2026-09-24, and EIA-923 2025. Page updated 2026-10-04. Data sources